> For the complete documentation index, see [llms.txt](https://intelfactor.gitbook.io/docs/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://intelfactor.gitbook.io/docs/home/validation/12-week-execution-plan.md).

# 12-week execution plan

A practical rollout plan that aligns with the acceptance gates.

This is a typical path from pilot to production.

### Weeks 1–2: Site discovery and constraints

* Network zoning decisions.
* Station inventory and camera placements.
* Evidence and retention requirements.

### Weeks 3–5: Pilot loop

* One station.
* Full evidence capture.
* Operator workflow validation.

### Weeks 6–8: Hardening

* Safe degradation tests.
* Observability baselines.
* Update + rollback rehearsal.

### Weeks 9–12: Scale-out

* Per-line rollout.
* RCA loop activation.
* Acceptance sign-off.

{% hint style="info" %}
Timelines vary by station count and OT change windows. Gates should not.
{% endhint %}